Progression of Sheffield Central build positive

Since the festive break, a number of achievements have been made, and many milestones met at the Sheffield Central site in the heart of the city centre. Following Christmas, work on the Pile Cropping and ring beam commenced from the car park end of the site. Work started along Eyre Lane and proceeded down Hallam Lane.


Achievements up to date (November 2018 - January 2019):


• The second part of the Site Investigation was completed

• Gas monitoring (Condition 3) was completed and submitted to Sheffield Council

• The site was back filled after archeological dig

• All existing perimeter walls were removed in preparation for the Piling Contractor

• The pile matting was installed in preparation for the Piling Contractor

• Installed temporary services (electric and water)

• Obtained party wall awards

• Completed the piling design

• Submitted piling and basement design to Highways

• Removed lamp posts

• Appointed Piling Contractor

• Ordered materials for basement

• Ordered steel frame

• Obtained party wall awards for the adjoining car park

• Ordered lifts

• Taken down the retaining wall

• Started piling

• Ordered window and external doors

• Ordered atrium roof

• Ordered roofing

• Ordered AOV and misting system

• Detailed the steel frame design

• Completed piling

• Activated the road closure of Eyre Lane

• Hoarded off Eyre Lane

• Site set up for groundworkers

• Started car park retaining wall

• Completion of the retaining wall

• Completion of the car park

• Continued pile cropping and ring beam (completed except entrance to allow wagons to carry out the reduced level dig)


Discover Sheffield Central here.


Our office hours:

Monday to Friday,

8.00am - 5.00pm

Call:

+44 (0)161 302 6732

Find us:

4th Floor, 2 Mount Street, Manchester, M2 5WQ

© Global Edge Ltd, 

Company No. 10739645

 

Privacy Policy

Website design by Global Edge